Importation of Size-Reduced Intermediate Level Waste (ILW) Skips from Oldbury, Sizewell 'A' and Dungeness 'A' Sites' for Interim Storage to Hinkley Point 'A', near Bridgwater, TA5 1YA

Decision Maker: Regulation Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Regulation Committee resolved that planning permissions SCC/3627/2019 and SCC/3628/2019 be REFUSED as the applicant has not successfully demonstrated that there is a requirement to amend the existing conditions (applications 3/32/16/018 and 3/32/17/005) that no radioactive waste shall be imported to the site from outside the Hinkley Point ‘A’ site to minimise detriment to the surrounding area.

 

Publication date: 06/09/2019

Date of decision: 05/09/2019

Decided at meeting: 05/09/2019 - Regulation Committee